Ground up Home Construction
- Posted 2 days ago
- United States (US)
Job description
Project Overview: Ground-Up Construction in the Palisades
Project Description
This project involves the ground-up construction of a 4,000 sq ft residential house in the Palisades, a coastal neighborhood known for its scenic views and high-end properties. The design will incorporate modern architectural elements, sustainable materials, and compliance with local zoning and building codes. The total estimated cost is based on $650 per sq ft, resulting in a construction budget of $2,600,000. The project timeline is estimated at 18-24 months, from permitting to final inspection, depending on approvals and weather conditions.Project Details
- Location: The Palisades, California
- Size: 4,000 sq ft
- Estimated Cost: $650/sq ft x 4,-clockwise- 4,000 sq ft = $2,600,000
- Timeline: 18-24 months
Milestones and Estimated Durations
1. Pre-Construction Phase (3-6 months)
- Tasks:
- Site survey and geotechnical investigation.
- Architectural design and drawings.
- Submission and approval of permits from the local Building and Safety Department.
- Selection of contractors and finalization of contracts.
- Milestone: Permit approval and groundbreaking.
- Estimated Duration: 3-6 months (depending on permit processing times).
2. Site Preparation and Foundation (2-3 months)
- Tasks:
- Site clearing, grading, and excavation.
- Installation of temporary utilities (power, water).
- Pouring of foundation and slab.
- Milestone: Completion of foundation, ready for framing.
- Estimated Duration: 2-3 months.
3. Structural Construction (4-6 months)
- Tasks:
- Framing of walls, floors, and roof.
- Installation of roof system and exterior walls.
- Structural inspections.
- Milestone: Structure is "dried-in" (weather-tight).
- Estimated Duration: 4-6 months.
4. Mechanical, Electrical, and Plumbing (MEP) Installation (3-4 months)
- Tasks:
- Installation of HVAC, electrical, and plumbing systems.
- Rough inspections for MEP systems.
- Milestone: MEP systems installed and inspected.
- Estimated Duration: 3-4 months.
5. Interior and Exterior Finishes (4-5 months)
- Tasks:
- Installation of drywall, insulation, and interior finishes (paint, flooring, cabinetry).
- Exterior finishes (siding, stucco, landscaping).
- Installation of fixtures, appliances, and trim.
- Milestone: House is move-in ready, pending final inspections.
- Estimated Duration: 4-5 months.
6. Final Inspections and Handover (1-2 months)
- Tasks:
- Final building inspections and certificate of occupancy issuance.
- Punch list completion (minor corrections and touch-ups).
- Client walkthrough and handover.
- Milestone: Project completion and client move-in.
- Estimated Duration: 1-2 months.
Total Estimated Timeline
- Duration: 18-24 months (from permitting to move-in).
- Assumptions: Timeline may vary due to weather, permit delays, or unforeseen site conditions.
Budget Breakdown
- Total Estimated Cost: $2,600,000
- Cost Breakdown (Approximate):
- Pre-Construction (design, permits): $100,000-$150,000
- Site Preparation and Foundation: $200,000-$300,000
- Structural Construction: $700,000-$900,000
- MEP Installation: $400,000-$500,000
- Interior/Exterior Finishes: $600,000-$800,000
- Final Inspections and Contingency: $150,000-$200,000
- Note: Costs include labor, materials, and contractor fees but exclude land acquisition, financing costs, or major unforeseen expenses.
Assumptions
- Site is buildable with no major geotechnical issues.
- Local permitting process follows standard timelines.
- No significant delays due to weather or material shortages.
- Client provides timely decisions on design and finishes.