Ground up Home Construction

  • Posted 2 months ago
  • United States (US)

Job description

Project Overview: Ground-Up Construction in the Palisades


Project Description


This project involves the ground-up construction of a 4,000 sq ft residential house in the Palisades, a coastal neighborhood known for its scenic views and high-end properties. The design will incorporate modern architectural elements, sustainable materials, and compliance with local zoning and building codes. The total estimated cost is based on $650 per sq ft, resulting in a construction budget of $2,600,000. The project timeline is estimated at 18-24 months, from permitting to final inspection, depending on approvals and weather conditions.

Project Details



  • Location: The Palisades, California

  • Size: 4,000 sq ft

  • Estimated Cost: $650/sq ft x 4,-clockwise- 4,000 sq ft = $2,600,000

  • Timeline: 18-24 months


Milestones and Estimated Durations


1. Pre-Construction Phase (3-6 months)



  • Tasks:

    • Site survey and geotechnical investigation.

    • Architectural design and drawings.

    • Submission and approval of permits from the local Building and Safety Department.

    • Selection of contractors and finalization of contracts.



  • Milestone: Permit approval and groundbreaking.

  • Estimated Duration: 3-6 months (depending on permit processing times).


2. Site Preparation and Foundation (2-3 months)



  • Tasks:

    • Site clearing, grading, and excavation.

    • Installation of temporary utilities (power, water).

    • Pouring of foundation and slab.



  • Milestone: Completion of foundation, ready for framing.

  • Estimated Duration: 2-3 months.


3. Structural Construction (4-6 months)



  • Tasks:

    • Framing of walls, floors, and roof.

    • Installation of roof system and exterior walls.

    • Structural inspections.



  • Milestone: Structure is "dried-in" (weather-tight).

  • Estimated Duration: 4-6 months.


4. Mechanical, Electrical, and Plumbing (MEP) Installation (3-4 months)



  • Tasks:

    • Installation of HVAC, electrical, and plumbing systems.

    • Rough inspections for MEP systems.



  • Milestone: MEP systems installed and inspected.

  • Estimated Duration: 3-4 months.


5. Interior and Exterior Finishes (4-5 months)



  • Tasks:

    • Installation of drywall, insulation, and interior finishes (paint, flooring, cabinetry).

    • Exterior finishes (siding, stucco, landscaping).

    • Installation of fixtures, appliances, and trim.



  • Milestone: House is move-in ready, pending final inspections.

  • Estimated Duration: 4-5 months.


6. Final Inspections and Handover (1-2 months)



  • Tasks:

    • Final building inspections and certificate of occupancy issuance.

    • Punch list completion (minor corrections and touch-ups).

    • Client walkthrough and handover.



  • Milestone: Project completion and client move-in.

  • Estimated Duration: 1-2 months.


Total Estimated Timeline



  • Duration: 18-24 months (from permitting to move-in).

  • Assumptions: Timeline may vary due to weather, permit delays, or unforeseen site conditions.


Budget Breakdown



  • Total Estimated Cost: $2,600,000

  • Cost Breakdown (Approximate):

    • Pre-Construction (design, permits): $100,000-$150,000

    • Site Preparation and Foundation: $200,000-$300,000

    • Structural Construction: $700,000-$900,000

    • MEP Installation: $400,000-$500,000

    • Interior/Exterior Finishes: $600,000-$800,000

    • Final Inspections and Contingency: $150,000-$200,000



  • Note: Costs include labor, materials, and contractor fees but exclude land acquisition, financing costs, or major unforeseen expenses.


Assumptions



  • Site is buildable with no major geotechnical issues.

  • Local permitting process follows standard timelines.

  • No significant delays due to weather or material shortages.

  • Client provides timely decisions on design and finishes.

Attachments available to download

Download project helping material provided by “2211 Homes”