The Power of Milestone Payments
Breaking your project into milestones creates natural checkpoints for progress verification and payment release. This structure protects both owners and contractors while keeping projects on schedule.
How to Structure Milestones
Typical Milestone Breakdown
For a major renovation project:
- Deposit - 10-20% upon contract signing
- Demo Complete - 15% after demolition
- Rough-In - 25% after framing, electrical, plumbing rough
- Drywall/Finish - 20% after walls complete
- Final - 20% upon completion and inspection
- Retention - 5% held for 30-60 days
California Retention Rules
Per California Civil Code §8814, retention is limited to 5% maximum. This protects contractors from excessive withholding while giving owners recourse for punch list items.
Using Bidroom's Milestone System
Our platform provides:
- Template-Based Setup - Use project templates for standard milestone structures
- Photo Documentation - Required uploads with each milestone
- Escrow Integration - Automatic payment release upon approval
- Lien Waiver Tracking - Required waivers before release
Best Practices
- Never pay more than 10% upfront before work begins
- Tie payments to verifiable completion points
- Require photo documentation with each submission
- Keep retention until all punch list items are complete
For complex projects, consider hiring a project manager to oversee milestone verification.