Typical Kitchen Renovation: 8-12 Weeks
A full kitchen renovation typically takes 8-12 weeks from demolition to completion. Here's what to expect.
Week 1-2: Demolition and Rough Work
- Existing cabinets, counters, and flooring removed
- Walls opened for inspection
- Any structural changes made
- Dust barriers installed
Week 3-4: Rough Mechanical
- Electrical rough-in for new outlets and lighting
- Plumbing rough-in for sink, dishwasher, ice maker
- HVAC adjustments if needed
- Inspections by city
Week 5-6: Walls and Flooring
- Drywall installed and finished
- Painting primer coats
- Flooring installation
Week 7-8: Cabinets and Countertops
- Cabinet installation (2-3 days)
- Countertop template (after cabinets)
- Countertop fabrication (1 week)
- Countertop installation
Week 9-10: Finish Work
- Backsplash installation
- Plumbing fixtures installed
- Electrical fixtures and outlets
- Appliance installation
Week 11-12: Final Details
- Final paint touch-ups
- Hardware installation
- Final inspections
- Walkthrough and punch list